The documentation package is a deliverable as physical as the pump. Every item below must be in the binder handed to the building owner at acceptance.

4.1 Required documents — NFPA 20 §14.4 / NBR 16704 §14.4

Document NFPA 20 NBR 16704 Format
Installation, Operation & Maintenance manual §14.4 §14.4 Bound print + searchable PDF, Portuguese
Pump performance curve (as-tested) §14.2 §14.2 Plot signed by witness
Pump nameplate photo §4.30 §4.27 Color photo at high resolution
Hydrostatic test certificate §14.1.4 §14.1.4 Lab-stamped certificate
HI 14.6 acceptance certificate (Grade 1U) §14.2.6 §14.2.6 Lab-stamped certificate
Vibration acceptance certificate §14.2.8 §14.2.8 Lab-stamped certificate
Coupling alignment record §6.4 §6.4 Field engineer signed
Driver — motor or engine certificates §9, §11 §9, §11 Manufacturer certificates
Controller listing certificate §10.1.2 §10.2 UL/FM listing copy
Transfer-switch listing certificate §10.8 §10.8 UL 1008 listing copy
As-built P&ID and pump-room drawing §14.4.1 §14.4 Stamped by registered PE
Spare-parts list (5 yr) §14.4.5 §14.4 Manufacturer document
Field-acceptance test report §14.2.6 §14.2.6 AHJ-witnessed
Maintenance schedule (weekly + annual) §8.3 §8.3-8.4 Building-owner sign-off
Operator training record §14.5 §14.6 Trainer + trainee signatures

4.2 Brazil-specific document items — NBR 16704

These have no NFPA 20 equivalent and must be in the package:

4.3 Document language

NBR 16704 §14.4 requires Portuguese as the primary language. NFPA 20 allows English. For a project in Brazil:

A package delivered exclusively in English will fail Bombeiros acceptance in most Brazilian states regardless of NFPA 20 conformity.

4.4 Document delivery

Format Required
Bound printed binder 2 copies — building owner + Bombeiros
USB / cloud-link with searchable PDFs 1 copy to building owner
Document index (this checklist annotated) 1 per copy

4.5 Sign-off

Field Entry
Documentation reviewed by _________
Reviewer organization _________
Date _________
All items present ☐ Yes ☐ No (list missing)
Missing items resolved by _________ (date)
Documentation accepted ☐ Yes ☐ No

Next stage: Corpo de Bombeiros field acceptance.