Skip to the content.

5. Factory acceptance — FAT witness rights

The Factory Acceptance Test is the buyer’s last chance to reject the pump while the vendor still has full leverage to fix it. Skipping FAT witnessing — or sending an unprepared witness — is the most common single procurement failure.

5.1 What FAT actually proves

A complete FAT measures:

Test Standard What it proves
Hydrostatic NFPA 20 §14.1.4 / API 610 §8.3.4 Casing integrity at 1.5× max working pressure
Performance curve HI 14.6 Q, H, η across full operating range
NPSHr by 3% drop HI 14.6 Cavitation onset point at multiple flows
Vibration HI 9.6.4 Mechanical assembly quality
Bearing temperature rise After 1 h continuous No interference, lubrication functioning
Mechanical alignment TIR ≤ 0.05 mm Coupling-to-driver concentricity
Visual / dimensional Buyer datasheet Casing, nozzle, bolt-pattern conformity
Documentation handover Buyer datasheet Manuals, certificates, drawings

A vendor who proposes “just hydrostatic and performance” is hiding the mechanical-quality measurements. Insist on the full set.

5.2 Pre-FAT preparation — buyer’s checklist

Two weeks before FAT:

If the vendor cannot produce calibration certificates for the test-bench instrumentation, the test is not valid by HI 14.6 standards. Reschedule until calibrated.

5.3 During FAT — the witness’s job

The witness is not a passenger. The witness’s job is to verify that:

  1. Test data is captured at the moment of measurement — not “we recorded that yesterday and have it on file”
  2. Each test point is held long enough for steady state — minimum 5 minutes per point
  3. Instrumentation matches the calibration certificates — physically verify serial numbers
  4. Discrepancies are flagged and signed in real time, not glossed over

Bring to FAT:

5.4 Performance curve verification

The single most-critical verification at FAT is the performance curve. Required at minimum:

If any point falls outside tolerance, the witness has these options written into the contract (clause 4.6):

  1. Accept with documented reservations
  2. Require re-test after vendor remedy
  3. Reject

Most witnesses default to (1) — and discover at site acceptance that the issue propagates. (2) is usually the right choice when the deviation is borderline; (3) is right when the deviation is structural (e.g., shut-off head exceeds 140% — a fundamental geometric mismatch).

5.5 NPSHr verification — the often-skipped step

NPSHr is measured by progressively dropping suction pressure until pump head drops 3%. This requires either:

What the witness should look for:

A vendor who “stamps” NPSHr from a previously-tested same-model unit without re-testing this serial number is shortcutting. NPSHr varies unit- to-unit by ±10% — your unit must be tested.

5.6 Mechanical tests

After hydraulic, the bench transitions to mechanical:

Test Method Pass criterion
Vibration Accelerometer at bearing housings RMS ≤ 5.0 mm/s (≤1.800 rpm) or ≤ 7.1 mm/s (>1.800 rpm)
Bearing temperature Thermocouple at bearing housing Rise ≤ 40 K, absolute ≤ 80 °C
Coupling alignment Dial indicator (cold) Parallel TIR ≤ 0.05 mm; angular TIR ≤ 0.05 mm/100 mm coupling diameter
Sound level dB(A) at 1 m from pump Per HI 9.4 OR contract spec
Lube oil sampling Visual + ferrous particle count No visible debris; ferrous count baseline established

Vibration is the most-skipped of these; insist on the spectrum plot, not just the overall RMS. A spectrum showing a strong 1× rotation peak indicates mass unbalance; 2× indicates misalignment; 1×N (N = blade count) indicates impeller hydraulic imbalance. Each has different remediation.

5.7 Documentation handover

At end of FAT, the buyer must receive:

If any document is incomplete, FAT is not signed off. Vendor will ship anyway because shipping is on their schedule, but the warranty clock should not start until documentation is complete and accepted.

5.8 FAT sign-off authority

The witness signature on the FAT certificate is binding. The witness should have:

Sending an unsupervised junior engineer to FAT is a common cost-saving move that produces tens of thousands of reais in remediation later.

The FAT witness is, for that day, the buyer’s hydraulic, mechanical, and contractual representative — staff accordingly.


Next section: Site acceptance and warranty.