Skip to the content.

6. Site acceptance and warranty — the next 12 months

The pump arrives, gets installed, gets commissioned, and the buyer’s attention moves to the next project. This is exactly when the most expensive procurement failures crystallize — silently, until the first unplanned outage proves them.

This section is the buyer’s guard rail for the first 12 months.

6.1 Receiving inspection at site

Within 5 business days of pump arrival on site:

Document any non-conformance immediately with photos. Do not sign the delivery acceptance until reservations are recorded; once signed clean, disputes are uphill.

6.2 Pre-installation storage

Pumps stored more than 30 days before installation need:

A common warranty-loss scenario: pump stored outdoors in tropical climate for 4-8 months, bearings corrode, fail at startup, vendor refuses warranty claim citing storage conditions. The vendor is generally right in this case. Storage discipline is the buyer’s responsibility.

6.3 Installation supervision

Vendor supervision during installation is usually optional in contracts — buy it anyway:

Vendor supervision typical cost: 1-3% of CAPEX for 2-5 days. Cost of self-installing wrong: ~25-50% of CAPEX in remediation plus warranty disputes.

The supervisor’s role is to certify, in writing, that the installation matches the manufacturer’s IOM manual. This certificate is what protects the warranty if a year-one failure occurs.

6.4 Commissioning — the gating event

Commissioning is the buyer’s last chance to validate FAT performance under real operating conditions:

Test Pass criterion
Cold start with no load Pump runs, alignment holds within FAT tolerance
4-hour run at 25-50% rated flow Bearing temperature stable, vibration within FAT
4-hour run at 75-100% rated flow Bearing temperature ≤ FAT temperature + 5 K
30-minute run at 110-120% rated flow No cavitation indication (sound, vibration)
Coupling alignment hot (after 2 h running) Within tolerance per supplier IOM
Lube oil sample No visible debris, ferrous count within baseline

Document each test in a commissioning report co-signed by the buyer’s project engineer and vendor’s representative. This is the artifact that starts the warranty clock per the contract.

6.5 First-year inspection schedule

In addition to the routine maintenance schedule, plan three buyer-led inspections in the first 12 months:

Month Inspection focus Why
1 Hot alignment re-check, vibration spectrum, bearing temp Verifies no settling-induced misalignment
6 Vibration trending, lube oil ferrous count, seal leakage Catches early bearing or seal issues while warranty is open
12 Full performance test (Q, H at duty point), efficiency, NPSH check Validates as-installed performance against FAT

Any deviation from FAT-baseline performance at month 12 is a warranty event if it exceeds tolerance bands. Document and trigger the warranty process before month 12 expires.

6.6 Warranty claim mechanics

When a warranty event occurs, follow the contractual process to the letter:

  1. Notice in writing within 5 business days of discovering the issue
  2. Photographs and operating data attached
  3. Reference to specific contract clause and performance guarantee
  4. Allow vendor reasonable access to inspect — typically 10-15 business days
  5. Joint root-cause investigation (vendor cannot refuse if contract has inspection rights)
  6. Repair / replace / refund per contract — buyer chooses where contract gives buyer choice

Common vendor pushback and the right response:

Vendor argument Buyer response
“Improper installation” Reference vendor-supervised installation certificate (§6.3)
“Operating outside specified envelope” Reference RFQ envelope spec (§1.2) and operating data
“Maintenance not performed per IOM” Reference maintenance log; show schedule was followed
“Wear-part consumable” Reference contract spare-parts clause; consumable wear is not warranty, but premature wear at 6 months is
“Force majeure” Document specific event invoked and contractual scope

6.7 Knowledge capture for next procurement

At month 12, hold an internal post-mortem:

Document the answers and feed them back into the procurement playbook. The next pump purchase — whether 6 months or 5 years from now — should be sharper than this one.

This is the rationale for Section 1 — Specifying being a living document, not a one-time SOP.


Back to README · Templates: RFQ · Evaluation matrix · TCO worksheet · Contract clauses